Data center · Facility
AnnouncedCoreWeave data center in Kenilworth, New Jersey
Announced Oct 2024, in Union County. No permit on record yet.
No permit on record yet. First seen Aug 15, 2026.
Where
Kenilworth, Union County, New Jersey.
Exact site not public. Shown at township level.
- Reported capacity
- 250MW
- Planned, as Compute Atlas (Jul 6, 2026) and Server Country (Sep 24, 2026) report it. 280,000 square feet, per Kapwork Grow tracker. May be planned, not energised, capacity.
- Work it brings
- Electrical, mechanical, low-voltage, site, fiber
- The trades a data center build hires, from the site work to the last mile of fiber.
- Who bills here
- CoreWeave
- The operator, per Compute Atlas and Server Country. No public record names its general contractor yet. The carriers show here when a record names them.
Nearest other build
ON3 Data Center (275 Kingsland Street)
12.8 miles away
Builds in Union County
Published build in the Kapwork Grow tracker, this one included. Published Nov 3, 2026.
Builds in New Jersey
Proposed, approved, under construction or expanding, this one included. Kapwork Grow tracker, published Nov 3, 2026.
U.S. data center construction
August 2026, seasonally adjusted annual rate, preliminary. Up 73.2% from $49.05B in August 2025; 63.3% of private office construction. U.S. Census Bureau, C30, released Oct 1, 2026.
What this means for you
Same customers, bigger invoices.
The electrical, mechanical and fiber work on this campus bills CoreWeave, its GC and the carriers you already know. Certify the invoices behind it, and funders compete to fund them.
An announced or permitted build is not a contract, an open bid or a purchase order.
Who your invoice goes to
- CoreWeaveOperator
- General contractorNot named yet
- CarriersNot named yet
- UtilityNot named yet
Key facts
- Stage
- Under constructionCompute Atlas · Jul 6, 2026; Server Country · Sep 24, 2026
- Reported capacity
- 250 MWCompute Atlas · Jul 6, 2026; Server Country · Sep 24, 2026
- Reported building area
- 280,000 sq ftKapwork Grow tracker · Nov 2, 2026
- Site area
- 27 acresKapwork Grow tracker · Nov 2, 2026
- Reported investment
- $1.8BKapwork Grow tracker · Nov 2, 2026
- Reported jobs
- 143Kapwork Grow tracker · Nov 2, 2026
- Announced
- Oct 2024Server Country · Sep 24, 2026
- Construction start reported
- Sep 2025Compute Atlas · Jul 6, 2026
- Expected completion
- 2027Server Country · Sep 24, 2026
- Location
- Kenilworth, Union County, New JerseyCompute Atlas · Jul 6, 2026; Server Country · Sep 24, 2026; Public Evidence Project · Aug 6, 2026
- Location precision
- Site footprint confirmedKapwork Grow tracker · Nov 2, 2026
- Community response
- Local opposition reportedKapwork Grow tracker · Nov 2, 2026
- Power source
- Grid powerKapwork Grow tracker · Nov 2, 2026
- Cooling
- Closed loopKapwork Grow tracker · Nov 2, 2026
- AI workload
- Confirmed AI or machine-learning workloadCompute Atlas · Jul 6, 2026
- Facility type
- AI data centerKapwork Grow tracker · Nov 2, 2026
- Incentives reported
- New Jersey EDA 'Next New Jersey — AI' tax credit — up to $250M ($50M/year for five years, performance-based, 10-year retention); CoreWeave was the first award under the program, which NJ later froze (New Jersey)Kapwork Grow tracker · Nov 2, 2026
- Government records on file
- 1Public Evidence Project · Aug 6, 2026
What the public record lacks: the general contractor's name.
Who's involved
- Operator
- CoreWeaveCompute Atlas · Jul 6, 2026; Server Country · Sep 24, 2026
- Tenants
- CoreWeaveKapwork Grow tracker · Nov 2, 2026
- Utility
- PSE&GKapwork Grow tracker · Nov 2, 2026
- General contractor
- Not named in a public record yet
- Carriers
- Appear here as the records name them
How far along it is
- · Server Country
Announced
- · Compute Atlas
Construction start
- · Kapwork's date
First seen in the Kapwork Grow tracker (its first snapshot)
- · Server Country
Expected completion
- Date not reported · Server Country
Expected completion reported
- Date not reported · Compute Atlas
Construction start reported
- Date not reported · Compute Atlas
Reported as announced
Dates as reported. Not a bid calendar. A planned date is not evidence that work occurred. Dates marked Kapwork's date come from the tracker's own snapshots, not from the sources.
More builds
Same operator
- 3301 Hibbetts Road Data CenterTexas
- C1 Richardson LLC Data CenterTexas
- CoreWeave Lancaster Data CenterPennsylvania
- Denton Data CenterTexas
- EdgeConneX AU02Texas
In New Jersey
- Andover HPC Data Center (former Newton Airport Site)New Jersey
- Bell Works Data Center (101 Crawfords Corner Road)New Jersey
- Chirisa PNJ-01 / PNJ-02 Piscataway CampusNew Jersey
- Comcast Clinton Data CenterNew Jersey
- Equinix NY3New Jersey
The Kapwork Grow tracker lists 11 published builds in New Jersey, as published Nov 3, 2026; these are the ones linked to this record.
Questions this page answers
Is CoreWeave NEST Campus under construction?
Who is building CoreWeave NEST Campus?
When is CoreWeave NEST Campus expected to finish?
Which carriers serve CoreWeave NEST Campus?
How do contractors on CoreWeave NEST Campus get paid sooner?
Already invoice CoreWeave?
Crews on a campus like this invoice the GC and the carriers in their own portals. Certify the unpaid invoices. Kapwork proves they're real so funders fund them sooner while the GC takes its time. Free for businesses.
- Multiple offers
- No notice of assignment
- Free for businesses
Sources, updates and data
Compute Atlas · Server Country · Public Evidence Project · Kapwork Grow tracker · U.S. Census C30
Where this comes from
- Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)
Record coreweave-kenilworth-nj · As of Jul 6, 2026 - Real Estate NJ (cited by Compute Atlas)
As of Jul 5, 2026 - News 12 New Jersey (cited by Compute Atlas)
As of Jul 5, 2026 - News 12 New Jersey (cited by Compute Atlas)
As of Jul 6, 2026 - Data Center Dynamics (cited by Compute Atlas)
As of Jul 6, 2026 - NJ Economic Development Authority (cited by Compute Atlas)
As of Jul 6, 2026 - Server Country project record (CC BY 4.0)
Record 0328 · As of Sep 24, 2026 - Public Evidence Project: Subsidy from NJ Economic Development Authority
Record source-coreweave-kenilworth-nj · As of Aug 6, 2026 - Kapwork Grow tracker record, merged from the sources listed here (free account)
Merged view of the sources here · snapshot Nov 2, 2026 - U.S. Census Bureau, Construction Spending (Value of Construction Put in Place, C30)
National data center spending · August 2026 · released Oct 1, 2026 - Kapwork Grow tracker
Counts, nearest build and first-seen dates (Kapwork's dates), published Nov 3, 2026. Tracker snapshot Nov 2, 2026; sources fetched: Compute Atlas Sep 24, 2026; Server Country Sep 24, 2026; Pennsylvania DEP Sep 24, 2026; EPA ECHO Sep 24, 2026; Texas Comptroller Sep 24, 2026; UVA DC-SENSE Sep 24, 2026; Public Evidence Project Sep 24, 2026.
What each source reports
- Compute Atlas: Under construction, 250 MW
- Server Country: Under construction, 250 MW
Updates
- Date not reported: Reported as announced. Compute Atlas
- Date not reported: Construction start reported. Compute Atlas
- Date not reported: Expected completion reported. Server Country
- 2027: Expected completion. Server Country
- Aug 15, 2026: First seen in the Kapwork Grow tracker (its first snapshot). Kapwork's date
- Sep 2025: Construction start. Compute Atlas
- Oct 2024: Announced. Server Country
Limitations and interpretation
- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-11-02. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0) · Public Evidence Project, U.S. Data Center Public Records Dataset, https://publicevidence.org/data/national-data-center-public-records (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
“Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.
Nearest build: Haversine great-circle distance on the tracker latitude and longitude, in statute miles, rounded to 0.1. First-seen dates: first_seen: the earliest committed snapshot of data/dcfo.sqlite holding any of the facility's source keys (source:source_id), narrowed to the nightly run day by the alert sender's facility_new events when they are available. status_first_seen: the start of the unbroken run of snapshots, ending at this one, in which a facility sharing a source key had the current status, narrowed by the latest status_changed event to that status. Dates are Kapwork's, not the sources'.
What we don't know yet
- The general contractor's name.
- The carriers that serve the campus.
- How the operator and its GC pay their contractors: portal, terms, days to pay.
Spot an error? Tell us