Douglas Electric Cooperative fiber build: 281 locations in Oregon. $1.4M award.

Not signed as of Nov 12, 2026Updated Sep 17, 2026Sources: NTIA federal reporting

Douglas Electric Cooperative Inc. holds a $1.4M BEAD award for a fiber build to 281 locations in Oregon. NTIA federal reporting carries it as of Sep 5, 2026. No signed agreement is linked to it as of Nov 12, 2026.

  1. Announced
  2. Won
  3. Signed
  4. Building
  5. Running
Awarded to Douglas Electric Cooperative
$1.4M
NTIA federal reporting, as of Sep 5, 2026
Planned locations
281
NTIA federal reporting, as of Sep 5, 2026
Technology
Fiber
NTIA federal reporting, as of Sep 5, 2026
Award status
Not reported
No signed agreement is linked to it as of Nov 12, 2026.

What this means for you

If you run fiber crews in Oregon, this is the vendor list to be on.

No signed agreement is linked to it as of Nov 12, 2026. Douglas Electric Cooperative contracts crews after it signs.

Data as of Nov 12, 2026
  • Striped: planned build window, NTIA federal reporting
  • Mint dot: data as of Nov 12, 2026

Mar 3, 2026 · Planned start

The start date the record gives. No dated construction record exists yet.

Not signed yet

No signed agreement linked as of Nov 12, 2026.

Feb 1, 2030 · Planned end

The record's planned completion. Certify what you have today so you're set up when this one lands.

The job in numbers

Holder
Douglas Electric Cooperative Inc.NTIA federal reporting, as of Sep 5, 2026
Reported award
$1.4MNTIA federal reporting, as of Sep 5, 2026
Planned locations
281NTIA federal reporting, as of Sep 5, 2026
Technology
FiberNTIA federal reporting, as of Sep 5, 2026
Planned window
Mar 3, 2026 to Feb 1, 2030NTIA federal reporting, as of Sep 5, 2026
Project code
CM61-BEAD-OR-85699NTIA federal reporting, as of Sep 5, 2026
State
OregonNTIA federal reporting, as of Sep 5, 2026

What the public record lacks: the county, the aerial and underground miles, the contractors and a signed agreement.

Numbers Kapwork worked out

None of these is in a source; redo the math from the facts beside them.

  • Award per location
    $5,000
    $1.4M ÷ 281 planned locations

How far along it is

Won. No signed agreement is linked to it as of Nov 12, 2026. Building needs its own dated record, and none exists yet.

  1. Sep 5, 2026
    In NTIA federal reporting (won)
  2. Not yet
    Subgrant agreement, as of Nov 12, 2026

Who's involved

Award holder
Douglas Electric Cooperative Inc.
State program
BEAD in Oregon
Contractor named
Appears here the day a record names one

Where

Oregon. The record carries no county for this award, so the county is open.

How to get on this job

Nothing public yet on how Douglas Electric Cooperative signs up crews or pays them.

A row appears here the day a source shows one, with that source beside it. Worked with Douglas Electric Cooperative? Tell us how they bring on subs and pay, and we'll add it with your source, named or not.

What this means for you

Two ways in.

Questions this page answers

Who holds BEAD award CM61-BEAD-OR-85699 in Oregon?
Douglas Electric Cooperative Inc. $1.4M for a fiber build to 281 locations, not signed as of Nov 12, 2026.
Is the Douglas Electric Cooperative fiber build signed?
Not yet. No signed agreement is linked to it as of Nov 12, 2026. The award is in NTIA federal reporting as of Sep 5, 2026.
What work does this build need?
The record lists fiber for 281 locations. No public record names the contractors yet.
When will this build start invoicing?
No public source dates it. The agreement is not signed yet, as of Nov 12, 2026. The record plans the build from Mar 3, 2026 to Feb 1, 2030.
How does a subcontractor on this build get paid sooner?
Once Douglas Electric Cooperative approves your invoice, certify it with Kapwork. Funders compete to fund it, so you don't wait for the payment date. Free for businesses. Kapwork doesn't lend and doesn't contact Douglas Electric Cooperative.

Turn what you're owed into cash before this lands.

Douglas Electric Cooperative has not signed yet, as of Nov 12, 2026. Certify the unpaid invoices you have from other customers today. Kapwork proves they're real so funders fund them sooner. Free for businesses.

  • Multiple offers
  • No notice of assignment
  • Free for businesses

Sources, updates and data

NTIA federal reporting · read Nov 12, 2026

Where this comes from

Updates

No dated updates yet.

What we don't know yet

  • The county; the record doesn't carry one.
  • The signed agreement; none linked as of Nov 12, 2026.
  • The aerial and underground miles.
  • The contractors on it.
  • How Douglas Electric Cooperative pays its crews: no public source.

Limitations

  • An award is a research signal. The award holder decides its own bids and subcontracts. Confirm project status and vendor needs with them.
  • The approval stage is inherited from a state-program milestone; individual project execution is not independently confirmed by that milestone.

An award is not an open solicitation, revenue, cash received, or guaranteed contractor demand. A planned date alone does not establish construction or completion. “Not reported” means missing information, not zero. Completed and withdrawn records can remain available as historical records.

Spot an error? Tell us

Cite: Kapwork Grow, “Douglas Electric Cooperative Inc. · Fiber · Oregon”, https://kapwork.com/grow/directory/bead/projects/oregon-broadband-project-cm61-bead-or-85699-pr_866e04021d72c3bb3c3d, materially updated Sep 17, 2026.

Report an error on this page.