# Site MAT 1177

> Proposed: a 1000 MW data center in Matagorda County, Texas, from the Kapwork Grow tracker (1 source). Sources and dates on every fact.

Page: https://kapwork.com/grow/directory/datacenters/site-mat-1177-tx-dc_83d230be1e1e  
Markdown: https://kapwork.com/grow/directory/datacenters/site-mat-1177-tx-dc_83d230be1e1e.md  
Updated: Nov 3, 2026  
Publisher: Kapwork Grow, a free directory of public records

MARA has proposed a 1000 MW data center in Matagorda County, Texas (proposed). One source reports this facility in the Kapwork Grow tracker. (Kapwork Grow tracker record, merged from the sources listed here, Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Nov 2, 2026)

## Facts

- **Operator:** MARA (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Jul 17, 2026)
- **Stage:** Proposed (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Jul 17, 2026)
- **Reported capacity:** 1000 MW (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Jul 17, 2026)
- **Site area:** 1,200 acres (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Reported investment:** $600.0M (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **County:** Matagorda (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Jul 17, 2026)
- **State:** Texas (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Jul 17, 2026)
- **Location precision:** Street address reported (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Facility type:** Enterprise (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)

## What each source reports

| Dataset | Reported name | Reported status | Reported MW |
| --- | --- | --- | --- |
| Compute Atlas | Site MAT 1177 | Proposed | 1000 MW |

## Questions this page answers

### Is Site MAT 1177 under construction?

No permit record shows it yet, so this page prints it as announced. Compute Atlas (Jul 17, 2026) reports it as proposed.

### Who is building Site MAT 1177?

MARA is the operator. No public record names the general contractor yet. It shows here the day one does.

### Which carriers serve Site MAT 1177?

No public record names them yet. They show here when a filing does.

### How do contractors on Site MAT 1177 get paid sooner?

The owner pays the general contractor, and the general contractor pays its subcontractors. Once your customer approves your invoice, certify it with Kapwork. Funders compete to fund it, so you don't wait for the payment date. Free for businesses. Kapwork doesn't lend and doesn't contact your customer.

## Latest updates

- [Reported as announced](https://www.stocktitan.net/news/MARA/mara-signs-agreement-with-hif-to-acquire-strategic-powered-land-site-nqvuby8e4d46.html). Reported for 2026.

## Related records

- [1102 McKinzie LLC Data Center](https://kapwork.com/grow/directory/datacenters/1102-mckinzie-llc-data-center-tx-dc_0127bf1ca258): Same state
- [1242 McKinzie LLC Data Center](https://kapwork.com/grow/directory/datacenters/1242-mckinzie-llc-data-center-tx-dc_aede5bcddc97): Same state
- [3301 Hibbetts Road Data Center](https://kapwork.com/grow/directory/datacenters/3301-hibbetts-road-data-center-tx-dc_a9c987c3868f): Same state
- [AUS 01 02 03 Data Center](https://kapwork.com/grow/directory/datacenters/aus-01-02-03-data-center-tx-dc_c2ec9cede7ed): Same state
- [AUS02 / Cedar Creek Campus](https://kapwork.com/grow/directory/datacenters/aus02-cedar-creek-campus-tx-dc_50d6bbdf6d66): Same state

## What this record does not show

- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-11-02. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

## Sources

- [Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)](https://www.stocktitan.net/news/MARA/mara-signs-agreement-with-hif-to-acquire-strategic-powered-land-site-nqvuby8e4d46.html) · as of Jul 17, 2026 · record mara-site-mat-1177-matagorda-tx
- [StockTitan (cited by Compute Atlas)](https://www.stocktitan.net/news/MARA/mara-signs-agreement-with-hif-to-acquire-strategic-powered-land-site-nqvuby8e4d46.html) · as of Jul 17, 2026
- [Crypto Briefing (cited by Compute Atlas)](https://cryptobriefing.com/marathon-digital-holdings-600m-texas-ai-bitcoin-campus/) · as of Jul 17, 2026
- [Kapwork Grow tracker record, merged from the sources listed here](https://kapwork.com/app/grow/datacenters/projects/site-mat-1177-tx) · as of Nov 2, 2026 · record 144938784136734

## Have an invoice your customer approved?

Certify your approved invoices. Funders compete to fund them. Multiple offers. No notice of assignment. Free for businesses.

- [Get offers](https://kapwork.com/app/register-originator?mode=express&flow=invoice_registration&source=growth_suite&intent=certify&return_to=%2Fapp%2Finvoices%2Fnew&entry_point=certify_public_directory)
- [Talk to an expert](https://meetings.hubspot.com/kylemase/kapwork-intro-with-kyle-mauricio)

## Cite this page

Kapwork Grow, "Site MAT 1177", https://kapwork.com/grow/directory/datacenters/site-mat-1177-tx-dc_83d230be1e1e, materially updated Nov 3, 2026.
