Google is building a 270 MW data center in Payne County, Oklahoma (under construction). 2 sources report this facility in the Kapwork Grow tracker. (Kapwork Grow tracker record, merged from the sources listed here, Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), Server Country project record (CC BY 4.0), as of Nov 2, 2026)

## Facts

- **Operator:** Google (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), Server Country project record (CC BY 4.0), as of Sep 24, 2026)
- **Stage:** Under construction (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), Server Country project record (CC BY 4.0), as of Sep 24, 2026)
- **Reported capacity:** 270 MW (estimate) (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Reported building area:** 1,800,000 sq ft (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Site area:** 400 acres (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Reported investment:** $3.00B (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Announced:** 2025-03 (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Sep 14, 2026)
- **Construction start reported:** Jul 21, 2026 (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Sep 14, 2026)
- **Expected completion:** 2027 (Server Country project record (CC BY 4.0), as of Sep 24, 2026)
- **City:** Stillwater (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), Server Country project record (CC BY 4.0), as of Sep 24, 2026)
- **County:** Payne (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), Server Country project record (CC BY 4.0), as of Sep 24, 2026)
- **State:** Oklahoma (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), Server Country project record (CC BY 4.0), as of Sep 24, 2026)
- **Location precision:** Site footprint confirmed (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Community response:** Local opposition reported (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Utility:** OG&E (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Power source:** Grid power (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **AI workload:** Confirmed AI or machine-learning workload (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Sep 14, 2026)
- **Facility type:** AI data center (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Incentives reported:** 25-year ad valorem (property-tax) exemption via a PILOT agreement with Stillwater/Payne County taxing jurisdictions (Stillwater Public Schools, Meridian Technology Center, Payne County, county health dept); PILOT payments rise 1%/yr, estimated ~$58.2M over 25 years for the first two phases (Stillwater / Payne County, OK) (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)

## What each source reports

| Dataset | Reported name | Reported status | Reported MW |
| --- | --- | --- | --- |
| Compute Atlas | Google Stillwater Data Center Campus | Under construction | Not reported |
| Server Country | Google Stillwater Data Center Campus | Under construction | Not reported |

## Questions this page answers

### Is Google Stillwater Data Center Campus under construction?

No permit record shows it yet, so this page prints it as announced. Compute Atlas (Sep 14, 2026) and Server Country (Sep 24, 2026) report it as under construction.

### Who is building Google Stillwater Data Center Campus?

Google is the operator. No public record names the general contractor yet. It shows here the day one does.

### When is Google Stillwater Data Center Campus expected to finish?

Server Country reports expected completion in 2027. That is a reported target, not a schedule.

### Which carriers serve Google Stillwater Data Center Campus?

No public record names them yet. They show here when a filing does.

### How do contractors on Google Stillwater Data Center Campus get paid sooner?

The owner pays the general contractor, and the general contractor pays its subcontractors. Once your customer approves your invoice, certify it with Kapwork. Funders compete to fund it, so you don't wait for the payment date. Free for businesses. Kapwork doesn't lend and doesn't contact your customer.

## Latest updates

- [Expected completion reported](https://servercountry.org/data/projects/). Reported for 2027.
- **Jul 21, 2026:** [Construction start reported](https://www.okenergytoday.com/2025/11/construction-gets-go-ahead-for-stillwater-data-center/)
- [Reported as announced](https://www.okenergytoday.com/2025/11/construction-gets-go-ahead-for-stillwater-data-center/). Reported for 2025-03.
- [Construction start reported](https://servercountry.org/data/projects/). Reported for 2025.
- [Reported as announced](https://servercountry.org/data/projects/). Reported for 2024-08.

## Related records

- [C1 Bosque I](https://kapwork.com/grow/directory/datacenters/c1-bosque-i-tx-dc_7f9d282375de): Same operator
- [Goodnight Campus](https://kapwork.com/grow/directory/datacenters/goodnight-campus-tx-dc_3577901dafbf): Same operator
- [Google - Council Bluffs Campus (Expansions)](https://kapwork.com/grow/directory/datacenters/google-council-bluffs-campus-expansions-ia-dc_d99d0146eb9f): Same operator
- [Google - LaGrange Campus](https://kapwork.com/grow/directory/datacenters/google-lagrange-campus-ga-dc_3fd6fe9c9bd0): Same operator
- [Google - Monroe County Campus](https://kapwork.com/grow/directory/datacenters/google-monroe-county-campus-ga-dc_0e8dbdf32952): Same operator
- [Aligned Data Centers Amber Site (Grady County)](https://kapwork.com/grow/directory/datacenters/aligned-data-centers-amber-site-grady-county-ok-dc_72541d6e90dd): Same state
- [American Tower EDC Oklahoma (Oklahoma City)](https://kapwork.com/grow/directory/datacenters/american-tower-edc-oklahoma-oklahoma-city-ok-dc_009a1469b166): Same state
- [BLE Landholdings Piedmont Data Center](https://kapwork.com/grow/directory/datacenters/ble-landholdings-piedmont-data-center-ok-dc_9bc46f1c21df): Same state
- [Beltline Energy Luther Data Center](https://kapwork.com/grow/directory/datacenters/beltline-energy-luther-data-center-ok-dc_0ee32653cdcf): Same state
- [Beltline Energy Oklahoma City Campus](https://kapwork.com/grow/directory/datacenters/beltline-energy-oklahoma-city-campus-ok-dc_c6e462a880b7): Same state

## What this record does not show

- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-11-02. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Server Country, https://servercountry.org/data/ (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.
- Capacity is estimated by the tracker from reported floor area at 150 W per square foot.

## Sources

- [Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)](https://www.okenergytoday.com/2025/11/construction-gets-go-ahead-for-stillwater-data-center/) · as of Sep 14, 2026 · record google-stillwater-ok
- [Oklahoma Energy Today (cited by Compute Atlas)](https://www.okenergytoday.com/2025/11/construction-gets-go-ahead-for-stillwater-data-center/) · as of Jul 6, 2026
- [Data Center Dynamics (cited by Compute Atlas)](https://www.datacenterdynamics.com/en/news/google-to-invest-9bn-in-cloud-and-ai-infrastructure-in-oklahoma/) · as of Jul 6, 2026
- [The Stillwegian (cited by Compute Atlas)](https://www.thestillwegian.news/2025-storylines-big-tech-comes-to-town/) · as of Jul 7, 2026
- [KFOR (cited by Compute Atlas)](https://kfor.com/news/local/payne-county-commissioner-raises-water-concerns-over-planned-google-data-center-complex-in-stillwater/) · as of Jul 7, 2026
- [Stillwater News Press (cited by Compute Atlas)](https://www.stwnewspress.com/news/update-stillwater-hoa-suing-google-over-claims-of-contamination-from-construction-site/article_350151c1-124a-405d-ad75-ca84c842556d.html) · as of Jul 7, 2026
- [News 9 (KWTV Oklahoma City) (cited by Compute Atlas)](https://www.news9.com/oklahoma-city-news/where-are-data-centers-are-being-built-oklahoma-list) · as of Jul 21, 2026
- [Public Radio Tulsa / StateImpact Oklahoma (cited by Compute Atlas)](https://www.publicradiotulsa.org/local-regional/2026-08-06/some-data-centers-are-building-their-own-power-plants-in-oklahoma-most-want-to-plug-into-the-grid) · as of Sep 14, 2026
- [Server Country project record (CC BY 4.0)](https://servercountry.org/data/projects/) · as of Sep 24, 2026 · record 0401
- [Kapwork Grow tracker record, merged from the sources listed here](https://kapwork.com/app/grow/datacenters/projects/google-stillwater-data-center-campus-ok) · as of Nov 2, 2026 · record 41200647219694

## Have an invoice your customer approved?

Certify your approved invoices. Funders compete to fund them. Multiple offers. No notice of assignment. Free for businesses.

- [Get offers](https://kapwork.com/app/register-originator?mode=express&flow=invoice_registration&source=growth_suite&intent=certify&return_to=%2Fapp%2Finvoices%2Fnew&entry_point=certify_public_directory)
- [Talk to an expert](https://meetings.hubspot.com/kylemase/kapwork-intro-with-kyle-mauricio)

## Cite this page

Kapwork Grow, "Google Stillwater Data Center Campus", https://kapwork.com/grow/directory/datacenters/google-stillwater-data-center-campus-ok-dc_2578c5f129ee, materially updated Nov 3, 2026.