# Cipher Stingray HPC Data Center

> Under construction: a 100 MW data center in Andrews County, Texas, from the Kapwork Grow tracker (2 sources). Sources and dates on every fact.

Page: https://kapwork.com/grow/directory/datacenters/cipher-stingray-hpc-data-center-tx-dc_b5bef1a0c174  
Markdown: https://kapwork.com/grow/directory/datacenters/cipher-stingray-hpc-data-center-tx-dc_b5bef1a0c174.md  
Updated: Nov 3, 2026  
Publisher: Kapwork Grow, a free directory of public records

Cipher Mining is building a 100 MW data center in Andrews County, Texas (under construction). 2 sources report this facility in the Kapwork Grow tracker. (Kapwork Grow tracker record, merged from the sources listed here, Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), Public Evidence Project: Filing from U.S. SEC (EDGAR), as of Nov 2, 2026)

## Facts

- **Operator:** Cipher Mining (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Jul 25, 2026)
- **Stage:** Under construction (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Jul 25, 2026)
- **Reported capacity:** 100 MW (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Jul 25, 2026)
- **Site area:** 250 acres (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Announced:** 2024-11 (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Jul 25, 2026)
- **Construction start reported:** Jul 17, 2026 (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Jul 25, 2026)
- **City:** Andrews (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), Public Evidence Project: Filing from U.S. SEC (EDGAR), as of Aug 6, 2026)
- **County:** Andrews (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), Public Evidence Project: Filing from U.S. SEC (EDGAR), as of Aug 6, 2026)
- **State:** Texas (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), Public Evidence Project: Filing from U.S. SEC (EDGAR), as of Aug 6, 2026)
- **Location precision:** Street address reported (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Facility type:** Enterprise (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Government records on file:** 1 (Public Evidence Project: Filing from U.S. SEC (EDGAR), as of Aug 6, 2026)

## What each source reports

| Dataset | Reported name | Reported status | Reported MW |
| --- | --- | --- | --- |
| Compute Atlas | Cipher Stingray HPC Data Center | Under construction | 100 MW |

## Questions this page answers

### Is Cipher Stingray HPC Data Center under construction?

No permit record shows it yet, so this page prints it as announced. Compute Atlas (Jul 25, 2026) reports it as under construction.

### Who is building Cipher Stingray HPC Data Center?

Cipher Mining is the operator. No public record names the general contractor yet. It shows here the day one does.

### Which carriers serve Cipher Stingray HPC Data Center?

No public record names them yet. They show here when a filing does.

### How do contractors on Cipher Stingray HPC Data Center get paid sooner?

The owner pays the general contractor, and the general contractor pays its subcontractors. Once your customer approves your invoice, certify it with Kapwork. Funders compete to fund it, so you don't wait for the payment date. Free for businesses. Kapwork doesn't lend and doesn't contact your customer.

## Latest updates

- **Jul 17, 2026:** [Construction start reported](https://www.sec.gov/Archives/edgar/data/1819989/000181998926000009/cifr-20251231.htm)
- [Reported as announced](https://www.sec.gov/Archives/edgar/data/1819989/000181998926000009/cifr-20251231.htm). Reported for 2024-11.

## Related records

- [Cipher Barber Lake Campus](https://kapwork.com/grow/directory/datacenters/cipher-barber-lake-campus-tx-dc_03dd695ac010): Same operator
- [Cipher Black Pearl Campus](https://kapwork.com/grow/directory/datacenters/cipher-black-pearl-campus-tx-dc_4ced631f3957): Same operator
- [Cipher Black Pearl LLC Data Center](https://kapwork.com/grow/directory/datacenters/cipher-black-pearl-llc-data-center-tx-2-dc_39fed3571082): Same operator
- [Cipher Colchis Campus](https://kapwork.com/grow/directory/datacenters/cipher-colchis-campus-tx-dc_284118881b62): Same operator
- [Cipher Digital Ulysses](https://kapwork.com/grow/directory/datacenters/cipher-digital-ulysses-oh-dc_a9d39e4082a6): Same operator
- [1102 McKinzie LLC Data Center](https://kapwork.com/grow/directory/datacenters/1102-mckinzie-llc-data-center-tx-dc_0127bf1ca258): Same state
- [1242 McKinzie LLC Data Center](https://kapwork.com/grow/directory/datacenters/1242-mckinzie-llc-data-center-tx-dc_aede5bcddc97): Same state
- [3301 Hibbetts Road Data Center](https://kapwork.com/grow/directory/datacenters/3301-hibbetts-road-data-center-tx-dc_a9c987c3868f): Same state
- [AUS 01 02 03 Data Center](https://kapwork.com/grow/directory/datacenters/aus-01-02-03-data-center-tx-dc_c2ec9cede7ed): Same state
- [AUS02 / Cedar Creek Campus](https://kapwork.com/grow/directory/datacenters/aus02-cedar-creek-campus-tx-dc_50d6bbdf6d66): Same state

## What this record does not show

- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-11-02. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0) · Public Evidence Project, U.S. Data Center Public Records Dataset, https://publicevidence.org/data/national-data-center-public-records (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

## Sources

- [Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)](https://www.sec.gov/Archives/edgar/data/1819989/000181998926000009/cifr-20251231.htm) · as of Jul 25, 2026 · record cipher-stingray-andrews-county-tx
- [U.S. SEC (EDGAR) (cited by Compute Atlas)](https://www.sec.gov/Archives/edgar/data/1819989/000181998926000009/cifr-20251231.htm) · as of Jul 17, 2026
- [Data Center Dynamics (cited by Compute Atlas)](https://www.datacenterdynamics.com/en/news/cipher-mining-acquires-more-than-500-acres-across-two-sites-in-texas-for-crypto-and-hpc-use/) · as of Jul 17, 2026
- [Report cited by Compute Atlas](https://www.globenewswire.com/news-release/2024/11/26/2987553/0/en/Cipher-Mining-Announces-Acquisition-of-New-Site-in-West-Texas-Adding-100-MW-of-Capacity-to-its-Growing-Portfolio-of-Power-and-Data-Center-Development-Opportunities.html) · as of Jul 25, 2026
- [Public Evidence Project: Filing from U.S. SEC (EDGAR)](https://www.sec.gov/Archives/edgar/data/1819989/000181998926000009/cifr-20251231.htm) · as of Aug 6, 2026 · record source-cipher-stingray-andrews-county-tx
- [Kapwork Grow tracker record, merged from the sources listed here](https://kapwork.com/app/grow/datacenters/projects/cipher-stingray-hpc-data-center-tx) · as of Nov 2, 2026 · record 199831702258036

## Have an invoice your customer approved?

Certify your approved invoices. Funders compete to fund them. Multiple offers. No notice of assignment. Free for businesses.

- [Get offers](https://kapwork.com/app/register-originator?mode=express&flow=invoice_registration&source=growth_suite&intent=certify&return_to=%2Fapp%2Finvoices%2Fnew&entry_point=certify_public_directory)
- [Talk to an expert](https://meetings.hubspot.com/kylemase/kapwork-intro-with-kyle-mauricio)

## Cite this page

Kapwork Grow, "Cipher Stingray HPC Data Center", https://kapwork.com/grow/directory/datacenters/cipher-stingray-hpc-data-center-tx-dc_b5bef1a0c174, materially updated Nov 3, 2026.