# AUS02 / Cedar Creek Campus

> Under construction: a 384 MW data center in Bastrop County, Texas, from the Kapwork Grow tracker (1 source). Sources and dates on every fact.

Page: https://kapwork.com/grow/directory/datacenters/aus02-cedar-creek-campus-tx-dc_50d6bbdf6d66  
Markdown: https://kapwork.com/grow/directory/datacenters/aus02-cedar-creek-campus-tx-dc_50d6bbdf6d66.md  
Updated: Nov 3, 2026  
Publisher: Kapwork Grow, a free directory of public records

EdgeConneX is building a 384 MW data center in Bastrop County, Texas (under construction). One source reports this facility in the Kapwork Grow tracker. (Kapwork Grow tracker record, merged from the sources listed here, Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Nov 2, 2026)

## Facts

- **Operator:** EdgeConneX (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Aug 16, 2026)
- **Stage:** Under construction (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Aug 16, 2026)
- **Reported capacity:** 384 MW (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Aug 16, 2026)
- **Site area:** 140 acres (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Reported investment:** $1.40B (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Construction start reported:** Mar 31, 2026 (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Aug 16, 2026)
- **City:** Cedar Creek (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Aug 16, 2026)
- **County:** Bastrop (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Aug 16, 2026)
- **State:** Texas (Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0), as of Aug 16, 2026)
- **Location precision:** Site footprint confirmed (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)
- **Facility type:** Enterprise (Kapwork Grow tracker record, merged from the sources listed here, as of Nov 2, 2026)

## What each source reports

| Dataset | Reported name | Reported status | Reported MW |
| --- | --- | --- | --- |
| Compute Atlas | AUS02 / Cedar Creek Campus | Under construction | 384 MW |

## Questions this page answers

### Is AUS02 / Cedar Creek Campus under construction?

No permit record shows it yet, so this page prints it as announced. Compute Atlas (Aug 16, 2026) reports it as under construction.

### Who is building AUS02 / Cedar Creek Campus?

EdgeConneX is the operator. No public record names the general contractor yet. It shows here the day one does.

### Which carriers serve AUS02 / Cedar Creek Campus?

No public record names them yet. They show here when a filing does.

### How do contractors on AUS02 / Cedar Creek Campus get paid sooner?

The owner pays the general contractor, and the general contractor pays its subcontractors. Once your customer approves your invoice, certify it with Kapwork. Funders compete to fund it, so you don't wait for the payment date. Free for businesses. Kapwork doesn't lend and doesn't contact your customer.

## Latest updates

- **Mar 31, 2026:** [Construction start reported](https://communityimpact.com/austin/bastrop-cedar-creek/government/2026/03/31/edgeconnex-plans-second-data-center-campus-in-bastrop-county/)

## Related records

- [Ashville Campus](https://kapwork.com/grow/directory/datacenters/ashville-campus-oh-dc_013459ba19e7): Same operator
- [ECX AUS11-16](https://kapwork.com/grow/directory/datacenters/ecx-aus11-16-tx-dc_a85334c4c3ed): Same operator
- [EdgeConneX - Elk Grove Village 2025 Data Center](https://kapwork.com/grow/directory/datacenters/edgeconnex-elk-grove-village-2025-data-center-il-dc_d123f9079e49): Same operator
- [EdgeConneX Cedar Creek Campus 2](https://kapwork.com/grow/directory/datacenters/edgeconnex-cedar-creek-campus-2-tx-dc_dfd7f6898e99): Same operator
- [EdgeConneX MCN New Albany (South Campus)](https://kapwork.com/grow/directory/datacenters/edgeconnex-mcn-new-albany-south-campus-oh-dc_d008a4e3bb05): Same operator
- [1102 McKinzie LLC Data Center](https://kapwork.com/grow/directory/datacenters/1102-mckinzie-llc-data-center-tx-dc_0127bf1ca258): Same state
- [1242 McKinzie LLC Data Center](https://kapwork.com/grow/directory/datacenters/1242-mckinzie-llc-data-center-tx-dc_aede5bcddc97): Same state
- [3301 Hibbetts Road Data Center](https://kapwork.com/grow/directory/datacenters/3301-hibbetts-road-data-center-tx-dc_a9c987c3868f): Same state
- [AUS 01 02 03 Data Center](https://kapwork.com/grow/directory/datacenters/aus-01-02-03-data-center-tx-dc_c2ec9cede7ed): Same state
- [AWS - Round Rock Data Center](https://kapwork.com/grow/directory/datacenters/aws-round-rock-data-center-tx-dc_8dfe2e65260c): Same state

## What this record does not show

- This record is the Kapwork Grow tracker's merged view of a facility, from the tracker snapshot built 2026-11-02. Facts tagged KW are the tracker's resolved values; the per-source rows it was merged from are listed under Sources and on the tracker record.
- Sources on this record: Compute Atlas: Kubiak, E. (2026). Compute Atlas [Data set]. https://doi.org/10.5281/zenodo.22284476 (CC BY 4.0). Every source is licensed for commercial use with attribution.
- An announced or permitted build is not a contract, an open bid or a purchase order.
- Capacity figures are as reported by the cited sources and may describe planned rather than energised capacity.

## Sources

- [Compute Atlas facility record (Kubiak, E., 2026, CC BY 4.0)](https://communityimpact.com/austin/bastrop-cedar-creek/government/2026/03/31/edgeconnex-plans-second-data-center-campus-in-bastrop-county/) · as of Aug 16, 2026 · record edgeconnex-cedar-creek-tx
- [Community Impact (cited by Compute Atlas)](https://communityimpact.com/austin/bastrop-cedar-creek/government/2026/03/31/edgeconnex-plans-second-data-center-campus-in-bastrop-county/) · as of Jul 17, 2026
- [Bastrop County Chamber (cited by Compute Atlas)](https://bastropcc.com/blog/edgeconnex-data-center-update-may-2026/) · as of Aug 16, 2026
- [Report cited by Compute Atlas](https://www.tdlr.texas.gov/TABS/Search/Project/TABS2025023484) · as of Jul 18, 2026
- [Kapwork Grow tracker record, merged from the sources listed here](https://kapwork.com/app/grow/datacenters/projects/aus02-cedar-creek-campus-tx) · as of Nov 2, 2026 · record 88883205205350

## Have an invoice your customer approved?

Certify your approved invoices. Funders compete to fund them. Multiple offers. No notice of assignment. Free for businesses.

- [Get offers](https://kapwork.com/app/register-originator?mode=express&flow=invoice_registration&source=growth_suite&intent=certify&return_to=%2Fapp%2Finvoices%2Fnew&entry_point=certify_public_directory)
- [Talk to an expert](https://meetings.hubspot.com/kylemase/kapwork-intro-with-kyle-mauricio)

## Cite this page

Kapwork Grow, "AUS02 / Cedar Creek Campus", https://kapwork.com/grow/directory/datacenters/aus02-cedar-creek-campus-tx-dc_50d6bbdf6d66, materially updated Nov 3, 2026.